Dillsboro Coffee Co - December 2022 Update

Room at open house

I'm learning a LOT about working with contractors and companies in a small town :)

  • The main room where people will order their coffee is now gutted.
  • The room on the east side of the building where people will sit and we'll do meetings and trainings is barely started.
  • We've decided to remove the bathroom on the main floor and build it out on the back "veranda".  This will give us 78 square feet more space in the seating area.   
  • The supply room is pretty much done.
  • The offices upstairs are waiting on drywall.

We're still waiting for heat in the building.  Our furnace guys were amazing (https://www.yellowpages.com/cross-plains-in/mip/stutlers-service-106280…) but we're waiting on the gas company to run a line to the building.  They're saying Tuesday after Christmas.  (it's only going to be 0 F on Christmas Day).

Still - we're encouraged - feeling like we're "on track".

Image
Room at open house
December 8th Open House
Image
Main room
Main area of the shop looking toward the front
Image
Seating area
This room will seat about 20 once this wall is removed